Union Valley Parkway Interchange

Description: In Santa Maria, on Route 101 at Union Valley Parkway. Construct interchange.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara
City
Zip Code 93455
 
Senate District
18
Assembly District 28
Congressional District 22
 
Caltrans District
05
 
 
County/State Route Santa Barbara 101
Postmile Begin/End 83.1 83.9
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  935    781  
Peak Period Time Savings (minutes)  5610    4518  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans David Beard (805)549-3016   david_beard@dot.ca.gov
Design (PS&E) Phase
Caltrans David Beard (805)549-3016   david_beard@dot.ca.gov
Right of Way Phase
Caltrans David Beard (805)549-3016   david_beard@dot.ca.gov
Construction Phase
Caltrans David Beard (805)549-3016   david_beard@dot.ca.gov
 
Corridor System Management Plan
Caltrans David Beard (805)549-3016   david_beard@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$6,098 $-1,656 $4,442
Non-bond Funding
State/Federal*
$8,384 $0 $8,384
Local**
$6,098 $-1,306 $4,792
Non Budgeted ETC
$0 $0 $0
 
Total**** $20,580 $-2,962 $17,618

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$2,486 $0 $2,486 $2,561
Design(PS&E)
$2,446 $0 $2,446 $2,640
Right of Way
$1,552 $0 $1,552 $1,685
Construction
$14,096 $-2,962 $11,134 $10,571
 
Total* $20,580 $-2,962 $17,618 $17,457

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/1999 

05/19/2009 
 

 
06/01/1999 

05/19/2009 
100  04/17/1999 

05/19/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/19/2009 

04/13/2012 
 

 
05/19/2009 

04/13/2012 
100  05/19/2009 

04/17/2012 


Begin Right of Way Phase

End Right of Way Phase
05/19/2009 

03/15/2012 
 

 
05/19/2009 

03/15/2012 
100  05/19/2009 

04/16/2012 


-1 
Begin Construction Phase

End Construction Phase
08/10/2012 

12/31/2013 
 

 
08/10/2012 

12/31/2013 
100  07/26/2012 

12/27/2013 


Begin Closeout Phase

End Closeout Phase
01/01/2014 

02/03/2015 
 

 
01/01/2014 

02/03/2015 
100  12/30/2013 

02/24/2015 


-1 
Corridor System Management Plan
Adoption Date 03/01/2013    06/06/2012  06/06/2012 
Implementation Date        
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 935 781
Peak Period Time Savings (minutes) 5610 4518

Bond Funding Cost
Adopted:
$6,098,000
Current Approved:
$4,792,000
Actual Expenditures:
$4,442,000

 

Status as of December 31, 2023.