Union Valley Parkway Interchange |
Description: In Santa Maria, on Route 101 at Union Valley Parkway. Construct interchange.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Barbara |
City | |
Zip Code | 93455 |
Senate District |
18 |
Assembly District | 28 |
Congressional District | 22 |
Caltrans District |
05 |
County/State Route | Santa Barbara 101 |
Postmile Begin/End | 83.1 83.9 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 935 | 781 |
Peak Period Time Savings (minutes) | 5610 | 4518 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | David Beard | (805)549-3016 | david_beard@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | David Beard | (805)549-3016 | david_beard@dot.ca.gov | |
Right of Way Phase |
Caltrans | David Beard | (805)549-3016 | david_beard@dot.ca.gov | |
Construction Phase |
Caltrans | David Beard | (805)549-3016 | david_beard@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | David Beard | (805)549-3016 | david_beard@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$6,098 | $-1,656 | $4,442 | ||||
Non-bond Funding | |||||||
State/Federal* |
$8,384 | $0 | $8,384 | ||||
Local** |
$6,098 | $-1,306 | $4,792 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $20,580 | $-2,962 | $17,618 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$2,486 | $0 | $2,486 | $2,561 | |||
Design(PS&E) |
$2,446 | $0 | $2,446 | $2,640 | |||
Right of Way |
$1,552 | $0 | $1,552 | $1,685 | |||
Construction |
$14,096 | $-2,962 | $11,134 | $10,571 | |||
Total* | $20,580 | $-2,962 | $17,618 | $17,457 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
06/01/1999 05/19/2009 |
|
06/01/1999 05/19/2009 |
100 | 04/17/1999 05/19/2009 |
1 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/19/2009 04/13/2012 |
|
05/19/2009 04/13/2012 |
100 | 05/19/2009 04/17/2012 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
05/19/2009 03/15/2012 |
|
05/19/2009 03/15/2012 |
100 | 05/19/2009 04/16/2012 |
0 -1 |
|
Begin Construction Phase
End Construction Phase |
08/10/2012 12/31/2013 |
|
08/10/2012 12/31/2013 |
100 | 07/26/2012 12/27/2013 |
1 0 |
|
Begin Closeout Phase
End Closeout Phase |
01/01/2014 02/03/2015 |
|
01/01/2014 02/03/2015 |
100 | 12/30/2013 02/24/2015 |
0 -1 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 03/01/2013 | 06/06/2012 | 0 | 06/06/2012 | 0 | ||
Implementation Date | 0 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 935 | 781 |
Peak Period Time Savings (minutes) | 5610 | 4518 |
Bond Funding Cost | |
---|---|
Adopted: |
$6,098,000 |
Current Approved: |
$4,792,000 |
Actual Expenditures: |
$4,442,000 |
Status as of December 31, 2023.